Solved

MS Project 2013 - actual finish date

Posted on 2015-01-14
1
213 Views
Last Modified: 2015-01-18
It takes 6 hrs to finish a task. The start date is 1/5 and the end date is 1/5. However, the actual end date is 1/10. I am using MS Project 2013 to keep track of this. When I changed the actual finish date to 1/10, it automatically updated Work to 45 hrs. The estimate Work is only 6 hrs, even though it spans several days. How do I fix this to show that the start date is 1/5, end date is 1/10, and Work/Actual Work is 6 hrs? Thanks
0
Comment
Question by:leblanc
1 Comment
 
LVL 6

Accepted Solution

by:
Brian Clausen earned 500 total points
ID: 40550373
I believe that MS Project has three settings for task type:
1. Fixed Units Task (where units is the number of resources allocated to a task per hour/day)
2. Fixed Work Task
3. Fixed Duration Task

You need to change the task from a Fixed Units Task to a Fixed Work Task.

If you have the setting on Fixed Units, it assumes one resource is working 6 hrs/day (or whatever rate you have configured) for the full project duration. Therefore, if you extend the duration, it assumes 6 hrs/day will be assigned on every working day (which increases the total hours worked).

If you change it to a Fixed Work Task, where the work is set at 6 hours, then the units will decrease as you extend the time (to 3/4 hr a day instead of 6 hrs a day)

You should be able to change this by clicking on the task in the Gannt chart, Click Task Information,  and then click the Advanced Tab. There should be a Task Type list where you can change the Task Type to 'Fixed Work'.

I apologize if the exact path is slightly different, if you have a different version of Project than I use.
0

Featured Post

Control application downtime with dependency maps

Visualize the interdependencies between application components better with Applications Manager's automated application discovery and dependency mapping feature. Resolve performance issues faster by quickly isolating problematic components.

Question has a verified solution.

If you are experiencing a similar issue, please ask a related question

Suggested Solutions

All of the resources available today make learning a new digital media easier than ever-- if you know where to begin. This is a clear, simple guide to a few of the basic digital art mediums and how to begin learning them on your own.
When we talk about DevOps toolchains, I sometimes wonder how many people really get what we’re talking about. I don’t know if it’s just semantics or tone or something else, but sometimes I think it just sounds like buzzword sausage. So it’s always …
The viewer will learn how to create a normally distributed random variable in Excel, use a normal distribution to simulate the return on an investment over a period of years, Create a Monte Carlo simulation using a normal random variable, and calcul…
The viewer will learn how to successfully download and install the SARDU utility on Windows 8, without downloading adware.

867 members asked questions and received personalized solutions in the past 7 days.

Join the community of 500,000 technology professionals and ask your questions.

Join & Ask a Question

Need Help in Real-Time?

Connect with top rated Experts

18 Experts available now in Live!

Get 1:1 Help Now