Microsoft Project Column for what is included in timeline

In MS Project 2013 I see I can add items to the timeline by clicking on them and adding one by one.  However, is there a column in the gnatt chart spreadsheet that I could mark like a yes or no for what is included.

Thanks!
Avatar of Phillip Burton
Phillip Burton

How about the Text1 column?
Avatar of HyperBPP

ASKER

Will the timeline only pick up the Text1 column?  What do I put there?  Yes/no?  I'm trying to allow people to mark it in spreadsheet gantt view so they don't have to click on each one and say "add to timeline"... only a minor time savings.
ASKER CERTIFIED SOLUTION
Avatar of Dr. Thomas Henkelmann
Dr. Thomas Henkelmann
Flag of Germany image

Link to home