summary task to add all previous tasks under it in addition to the automatic single subtask

Hi

I had some tasks in MS Project Management 2010 that were created prior to me creating a summary task. Now I want the summary task to add all the time for those previous tasks in addition to the automatic single task  the summary task created. How can I get that done?

Thanks
LuckyLucksAsked:
Who is Participating?

[Product update] Infrastructure Analysis Tool is now available with Business Accounts.Learn More

x
I wear a lot of hats...

"The solutions and answers provided on Experts Exchange have been extremely helpful to me over the last few years. I wear a lot of hats - Developer, Database Administrator, Help Desk, etc., so I know a lot of things but not a lot about one thing. Experts Exchange gives me answers from people who do know a lot about one thing, in a easy to use platform." -Todd S.

Delphineous SilverwingGood Ol' GeekCommented:
Project assumes tasks are run in parallel, unless the dependency is set. Subtasks need to be chained (dependency of previous task set) in order for the total time to be calculated at the main task.
0

Experts Exchange Solution brought to you by

Your issues matter to us.

Facing a tech roadblock? Get the help and guidance you need from experienced professionals who care. Ask your question anytime, anywhere, with no hassle.

Start your 7-day free trial
BarbM60604Commented:
Move the individual tasks under the summary task and indent until they become part of the summary task
0
It's more than this solution.Get answers and train to solve all your tech problems - anytime, anywhere.Try it for free Edge Out The Competitionfor your dream job with proven skills and certifications.Get started today Stand Outas the employee with proven skills.Start learning today for free Move Your Career Forwardwith certification training in the latest technologies.Start your trial today