How to set end date in MS Project 2010, so that all other tasks are set accordingly
Hello,
I have MS Project 2010 Gantt chart and I have a hard end or stop deadline for a project. How do I create the Gantt chart so that when I have this task with the hard deadline date, all other dates ahead of it get adjusted automatically? For example, if I have fixed durations for task 1, 2, and 3, and then change the Go Live date, start and end dates are changed automatically.
Task Start Date End
-------------------------- ---------- ----
Task 1 4/21/15 4/28/15
Task 2 4/28/15 5/10/15
Task 3 5/10/15 5/18/15
Go Live 5/18/15 5/18/15
I have MS Project 2010 Gantt chart and I have a hard end or stop deadline for a project. How do I create the Gantt chart so that when I have this task with the hard deadline date, all other dates ahead of it get adjusted automatically? For example, if I have fixed durations for task 1, 2, and 3, and then change the Go Live date, start and end dates are changed automatically.
Task Start Date End
--------------------------
Task 1 4/21/15 4/28/15
Task 2 4/28/15 5/10/15
Task 3 5/10/15 5/18/15
Go Live 5/18/15 5/18/15