Using formulas in MS Project to indicate status of each task

I want to add a Green, Yellow, Red status indicator to tasks in a project plan without having to do this manually.
Essentially for each tasks the rules are as follows:
1)  If the task Completion % = 100, then the task is complete and therefore Green
2)  if the task Completion % <100 and today's date is 1 day from the Finish date, then the task has the potential of being Late and therefore Yellow
3) if the task Completion % <100 and the Finish date is < today's date, the task is late and therefore Red
4) Else task is Green  

My Excel skills in writing formulas is not working for me in MS Project :(
jlove88Program ManagerAsked:
Who is Participating?

Improve company productivity with a Business Account.Sign Up

x
 
Jackie ManConnect With a Mentor Commented:
I did a quick search and the finding is as follows:


If you are using MS Project 2010 or later, the field names have changed.  Use the following formula:

IIf([Scheduled Duration]=0,(IIf([% Complete]=100,5, IIf([Scheduled Finish]<Now()+7 And [% Complete]<100 And [% Complete]>=80,3,IIf([Scheduled Finish]<Now()+7 And [% Complete]<80,4,1)))),IIf([% Complete]=100,5, IIf([% Complete]>=100*(Abs(ProjDateDiff([Scheduled Start],Now())/ProjDateDiff([Scheduled Start],[Scheduled Finish]))),2,(IIf([Scheduled Finish]>Now(),IIf([Scheduled Start]>Now(),1,3),4)))))

Source: http://blog.practicingitpm.com/2013/08/25/improved-calculated-status-indicator-ms-project/
0
 
Jackie ManCommented:
In short, it is to create a custom field with the value of the formula and display the results in respective color according to the value.
0
 
xtermieCommented:
You can actually add the indicators built-in MS project, which can also be customized
The process is fully described here:
https://support.office.com/en-us/article/Add-indicators-09EE6A60-E171-431A-8E1D-58ADC2A317CF?ui=en-US&rs=en-US&ad=US
0
 
jlove88Program ManagerAuthor Commented:
Worked like a charm.  Thank you
0
Question has a verified solution.

Are you are experiencing a similar issue? Get a personalized answer when you ask a related question.

Have a better answer? Share it in a comment.

All Courses

From novice to tech pro — start learning today.