Solved

MS Project - 24 hour Working Days

Posted on 2016-11-20
3
44 Views
Last Modified: 2016-11-20
I've created a new project in MS Project 2010 and am using the standard 24 hour calendar. That seems to do what I want it to do - to a point. If I have a task (let's call it Task 31) with a 3-hour duration that starts on Wednesday at 10:00 PM, MS Project correctly sets the task's Finish Date to be Thursday at 1:00 AM. I have another task (let's call it Task 32) with a 4 hour duration and its predecessor is Task 31. MS Project correctly sets the Start Date of Task 32 to Thursday at 1:00 AM and its Finish Date to Thursday at 5:00 AM.

So far, so good

The problem that I am having is lunch time. Apparently, MS Project assumes that we don't work on any day from noon to 1:00 PM. Because that is not true (we work 24 hours a day, 7 days a week, and have no break times at all)  I need to change that default but can't figure out how. There must be a simple setting somewhere to do this.

Let's say, for example that I define a task (call it Task 35) that has a duration of 2 hours and begins on Tuesday at 10:00 AM. MS Project correct sets the task's Finish Date to Tuesday at noon. I have another task (call it Task 36) with a duration of 2 hours and its predecessor is Task 35. MS Project sets that task's Start Date to Tuesday at 1:00 PM. I don't want that. I want it to set the task's Start Date to Tuesday at noon - no lunch break.

Hope someone out there can let me know how to set this as a default in my project. There must be a simple way to do this that I'm just not seeing.

Thanks in advance for your help.
0
Comment
Question by:cbridgman
  • 2
3 Comments
 
LVL 48

Accepted Solution

by:
PortletPaul earned 500 total points
ID: 41895228
Navigate to [Project] and then to [Change Working Time]

There you can re-define the work time to remove the lunch period

see:
https://support.office.com/en-us/article/Set-the-general-working-days-and-times-for-a-project-c4587751-2b88-449d-87e5-d3312d16771d

{+edit} You can also change you calendar to the "24 Hours" calendar, look at the list of calendars available at the tiop of the "Change Working Time" dialog
0
 

Author Comment

by:cbridgman
ID: 41895232
I think I finally figured it out ... What a pain this is. You'd think it would be easier.

Anyway, I followed all of the steps required to make / use a 24 hour calendar, 7 days a week but MS Project still wanted to make me eat lunch. I finally found something else - the resource sheet. I had to go to the resource sheet and assign each resource to the 24 hour calendar. Once I did that, I was no longer forced to eat lunch
0
 

Author Closing Comment

by:cbridgman
ID: 41895234
Thanks for your help
0

Featured Post

Best Practices: Disaster Recovery Testing

Besides backup, any IT division should have a disaster recovery plan. You will find a few tips below relating to the development of such a plan and to what issues one should pay special attention in the course of backup planning.

Question has a verified solution.

If you are experiencing a similar issue, please ask a related question

Article by: x-men
Where used to see Gantt charts for illustrating project timelines, but what if I wanted to visualize passed timed events? Here's how.
Online collaboration is quickly becoming embedded in the workplace, and its benefits are tangible. See what the current landscape looks like and what the future holds for collaboration tools and the future of work.
This video shows how to use Hyena, from SystemTools Software, to bulk import 100 user accounts from an external text file. View in 1080p for best video quality.

809 members asked questions and received personalized solutions in the past 7 days.

Join the community of 500,000 technology professionals and ask your questions.

Join & Ask a Question