How can I set cell value Layer 1 'pins'.Visibility (or print) on [Page-1] to cell value Scratch 1 X on [Page-2]? I've tried formulas like
Shapesheet-Cell-Referencing.png
Pages[Page-1]!ThePage!Layers...
. but could never find a proper way to reference either the 'Print' or 'Visibility' value. A brief web search does not seem to provide the answer I'm looking for.Shapesheet-Cell-Referencing.png
ASKER CERTIFIED SOLUTION
membership
This solution is only available to members.
To access this solution, you must be a member of Experts Exchange.
ASKER
Open in new window
The next question would be weather or not there is a way to reference the layer by name. I can see now that as I work on a document and add more pages and parts to the schematics that I will not be able to rely on a consistent layer numerical order so I'll need to be able to reference the layer by name.