Project tasks time minimum

Cered
Cered used Ask the Experts™
on
Is there any project management software that will allow a task to have a duration of less than a minute?  Is there a way for Microsoft Project to all for this?  (setting ".5 minute" does not really work)

Thanks
Comment
Watch Question

Do more with

Expert Office
EXPERT OFFICE® is a registered trademark of EXPERTS EXCHANGE®
System Analyst
Commented:
In the Duration column for the task, type the duration in minutes (m), hours (h), days (d), weeks (w), or months (mo).

NOTE: Project does not convert the units if you change them. For example, if the duration is 1 day and you want to express it in hours, you must first calculate the number of working hours in a day and then enter the new value in hours.
PortletPaulEE Topic Advisor
Most Valuable Expert 2014
Awarded 2013

Commented:
The minimum time unit for duration is 1 minute.
Up to an including MSP 2013 - and I'm pretty sure it continues this wayminimum unit is: Minutes
What is it that you are attempting to do?
Does the time unit actually matter?

Author

Commented:
It does matter.  We use project to track a roll over of a disaster recovery plan, and there are some steps that take 15 seconds to complete.  If we put it down as 0 minutes then it becomes a mile stone  which distorts the critical path.  if I mark the time as 1 minute then, since there are 200 tasks in this project; it invalidates my timeline.
PortletPaulEE Topic Advisor
Most Valuable Expert 2014
Awarded 2013

Commented:
Thanks. I understand now. I'm afraid there is nothing more i can suggest.