MS Project Exported in Excel format issue

Hello,

As I work in MS Project, and export data to Excel, thru mapping, I seem to be missing on:

1) Exporting Task Name - I cannot find proper field name to map
2) The Start and Finish dates exported don't allow me change their format
3) Assignment Column has value only 'No'

Warm regards,

Sanjay.
Home-Move.xlsx
Sanjay GandhiFounder, KenhalAsked:
Who is Participating?
 
PortletPaulConnect With a Mentor freelancerCommented:
As Is export looks like this: msp-export-sample.pngFor the date columns, choose a date format (in MSP) that is yyyy-MM-dd hh:mm OR MM-dd-yyyyy hh:mm OR dd-MM-yyyy hh:mm depending on the "native" date style you use in Excel. The date format used is a string because of the month names.The column that has the resource in a coma seperated list is called (from memory) "Resources".

Please note I no longer have MSP to refer to so i can't offer much more detail.

nb: if you don't export the MSP row numbers how will the predecessor references be useful? (the do not align to Excel's row numbers)
0
 
Sanjay GandhiFounder, KenhalAuthor Commented:
Got it.

I also got the answer that while exporting if I choose buttons "base on table", and then select "Entry", I get my answer on ID, Task Name and even Resource assignment.

Besides, the above help should be really good.

San.
0
Question has a verified solution.

Are you are experiencing a similar issue? Get a personalized answer when you ask a related question.

Have a better answer? Share it in a comment.

All Courses

From novice to tech pro — start learning today.