How can you sort Microsoft Project 2013 tasks by date that are in different subtask sections?

Hi,
How can you sort Microsoft Project tasks by date that are in different subtask sections?
I have 500+ task with a task on line 11, 25, 143, 175 & 400 (different subtask sections) all occurring on the same day.
The sort option (down arrow in the Start and Finish title bar) only completes a sort within each of the subtask sections.

Thank you for your assistance.
Scott
stepnharpAsked:
Who is Participating?

[Product update] Infrastructure Analysis Tool is now available with Business Accounts.Learn More

x
I wear a lot of hats...

"The solutions and answers provided on Experts Exchange have been extremely helpful to me over the last few years. I wear a lot of hats - Developer, Database Administrator, Help Desk, etc., so I know a lot of things but not a lot about one thing. Experts Exchange gives me answers from people who do know a lot about one thing, in a easy to use platform." -Todd S.

stepnharpAuthor Commented:
Solved.  Found on other forum.

Go to View > Data group > Sort > Sort by to bring up the Sort window. Then uncheck the "keep outline structure" option near the bottom of the Sort window.
0

Experts Exchange Solution brought to you by

Your issues matter to us.

Facing a tech roadblock? Get the help and guidance you need from experienced professionals who care. Ask your question anytime, anywhere, with no hassle.

Start your 7-day free trial
It's more than this solution.Get answers and train to solve all your tech problems - anytime, anywhere.Try it for free Edge Out The Competitionfor your dream job with proven skills and certifications.Get started today Stand Outas the employee with proven skills.Start learning today for free Move Your Career Forwardwith certification training in the latest technologies.Start your trial today
Project Management Software

From novice to tech pro — start learning today.