lianne143
asked on
Sequence of Safely shutting down servers and powering on again.
Hi
We have new infrastructure with Dell Power Edge servers with DELL Powervault ME4 storage connected with 12G SAS.
We use VMware Vcenter appliance.
I have powered off the old servers. Now I would like to shut down the new infrastructure safely and move the servers to a different rack and power on the servers again.
Please post me sequence of shutting down and powering on the server’s safety, including core switches.
Thanks and suggestion much appreciated.
We have new infrastructure with Dell Power Edge servers with DELL Powervault ME4 storage connected with 12G SAS.
We use VMware Vcenter appliance.
I have powered off the old servers. Now I would like to shut down the new infrastructure safely and move the servers to a different rack and power on the servers again.
Please post me sequence of shutting down and powering on the server’s safety, including core switches.
Thanks and suggestion much appreciated.
ASKER CERTIFIED SOLUTION
membership
This solution is only available to members.
To access this solution, you must be a member of Experts Exchange.
ASKER
Thanks for all your help!
np
Unfortunately, if any part of it is not redundant, you will need to safely shut down the entire thing to make the move. I did make one live move with a unit that had dual power supplies. Everything else was redundant except that one unit, but it did have 2 power supplies. That is not something that I'd recommend, but it can be done. You just have to be careful not to accidentally pull out both power plugs at the same time. Good thing the place was chilled, or I'd be sweating bullets until it was done.